[Construction Case] Industrial Waste Factory: Floor Slab Void Filling Work
The impact of weak ground! Introducing a case where 100% filling without gaps eliminated voids and cavities under the floor.
We would like to introduce a case of "filling voids and cavities under the concrete floor" carried out at a waste disposal facility in Chiba Prefecture. Due to the influence of weak ground, the ground subsided, creating large voids under the concrete floor. We injected polyurethane resin under the concrete to fill the voids. After construction, it can be visually confirmed that polyurethane resin has been filled directly beneath the areas where the concrete floor was excavated. [Case Overview] - Construction Area: Approximately 710m² - Maximum Void: 180mm - Area: Chiba Prefecture - Construction Period: 4 days *For more details, please refer to the PDF document or feel free to contact us.